Option 1 consists of the removal of the existing east and west portions of the pier and replacing them with the construction of a new pier in the same footprint. This option could be used to best mimic the original pier as it would be constructed in the same location. To preserve the functionality of the building, a temporary trestle could be constructed to access the restaurant during construction. It is often considered more economical to construct piers using the top-down method but due to the site limitations needed to get past the existing restaurant to perform this method, a temporary bypass trestle would need to be constructed to allow construction equipment to get around the existing restaurant.
Option 2 consists of the construction of a new pier adjacent to the existing pier that runs along the south side of the existing with a new connection provided for the restaurant. The entrance to the pier would be located further south in the park than what currently exists. This option would also return the pier back to its original length. One benefit of this option is that the existing pier and restaurant could remain open without any temporary access required during construction. After the new pier is constructed the existing pier on the west and east side could be demolished. This option would tie the new pier into the south side of the restaurant in lieu of the west side that the current pier configuration has. Another benefit of this option is that top-down construction could be easily done without the need for a temporary bypass trestle. This option would be contingent on the City obtaining a new submerged land lease.
Option 3 is a combination of the two options mentioned above configured in the hope of minimzing potential permitting obstacles. The new pier would be constructed in the same footprint as the existing to the west of the restaurant under the existing submerged land lease, then the pier would turn southward and wrap around the restaurant before extending eastward back to the pier’s original length. Like Option 1, temporary access to the restaurant would need to be in place during construction. This option would also allow for top-down construction since the proposed pier runs a continuous path, not getting interrupted by the existing restaurant. This option would keep the same entrance point to the pier as the existing (on the north side of the park). This configuration has more square footage of the pier than the existing or original pier. Special consideration may be required to how much area is dedicated to fishing and restrictive fishing areas may need to be implemented, and this option would also be contingent on the City obtaining a new submerged land lease.