WGI was responsible for study, design, permitting, surveying and mapping and construction phase services for water and sewer utility services in residential special assessment districts. Services also included utility conflict resolution and accommodations for existing improvements.
Project List Includes:
- CHERYL LANE
Water Main 6” – 640 linear feet | Construction Cost - $93,065.06
- EDNE & KATHY LANE
Water Main 8” – 740 linear feet | Water Main 6” – 830 linear feet
Construction Cost - $136,242.32
- LAGO DEL SOL
Water Main 4” through 8” – 4,210 linear feet | Construction Cost - $352,792.16
- DILLMAN HEIGHTS
Water Main 4” through 6” – 5,791 linear feet | Construction Cost - $583,986.50
- HORSESHOE ACRES
Water Main 4” through 12” – 13,510 linear feet | Construction Cost - $352,792.16
- SUNCREST ROAD
Water Main 6” – 2,760 linear feet | Construction Cost - $232,204.65