WGI Icon_Green (1)
WGI Projects
Project Experience

Learn more about successful projects from some of our clients.

Plan Your Next Project!

Kick-start your next project with this quick step-by-step intake form.
About
WGI

WGI is a national design firm creatively transforming infrastructure and real estate through tech-driven services.

Our
Locations

You’ve seen our award-winning team, proven expertise, and industry authority. Now let’s make your next project a success.

Meet Our
Leadership Team

Our Executive Leadership Team and Practice Area Leaders bring decades of experience and client successes to your next project.

Our Practice Area Leadership

Our nationwide team of engineers, surveyors, planners, and architects offers
market-leading experience.

Firm Registrations

WGI holds nationwide registrations to perform engineering, surveying, architecture, and environmental science services.
WGI
Insights Blog

Our blog covers client interests like infrastructure, real estate, regulations, and smart, connected communities.

Whitepapers & Publications

Our whitepapers highlight our design experts' innovative insights and best practices for the AEC industry.

News &
Press Releases

Dedicated to your success, we invite you to subscribe to our newsletter for the latest news, case studies, and insights.

WGI
Media Room

Our passionate design professionals frequently share their expertise at webinars and virtual events.

Thomas Street Stormwater Pump Station

Client:
Mock Roos
Market:
Water & Environment, Stormwater Management
Location:
Delray Beach, Florida

Project Details

In 2019, a Stormwater Master Plan was developed for the City of Delray Beach (City) to evaluate the potential of increasing the pumping capacity of the Thomas Street Pump Station for both current and 30-year Sea Level Rise tidal conditions. The existing stormwater facility provides protection to a 50-acre drainage basin including Thomas Street, Vista Del Mar Drive, and part of Andrews Avenue and Lowery Street. Located at the end of Thomas Street, the facility pumps water back into the Intracoastal Waterway through an outflow pipe, roughly one foot wide. When water levels are elevated during high tide and heavy rain, the pipe opens and closes for three-minute intervals to alleviate flooding. However, the existing facility is undersized and past its life expectancy.

The City Commission reviewed data for areas most vulnerable to sea level and groundwater rise and determined the Thomas Street Pump Station was highest on the list of capital improvement priorities. The City selected Mock Roos to provide preliminary engineering, designing, permitting, bidding, and post-design services of the stormwater pump station replacement facility. As part of Mock Roos’ team, WGI, Inc. (WGI) provided full survey design services, including right-of-way mapping, topographic surveying, hydrographic surveying, and subsurface utility engineering to assist with the design plans.

WGI utilized mobile LiDAR, a complete mobile mapping, and survey solution, to collect accurate and detailed data through sensors. This solution promotes increased safety by avoiding the need for the field staff to work within the travel lanes and avoid trespassing on private property due to the proximity of this residential neighborhood. The City also requested WGI to obtain finished floor elevations (FFE) for the entire Thomas Street Drainage Basin. WGI was able to measure 90% of all FFE from the mobile LiDAR collection. The vertical accuracy was maintained for this data by digitally leveling throughout the basin. Due to the quick collection of field data, WGI provided a merged file of all services ahead of schedule.

Project at a Glance

  • Thomas Street Stormwater Pump Station — image 1
  • Thomas Street Stormwater Pump Station — image 2